Steam filter station (D) 

Contract volume: 14.2 Mio.€

Subject: STEAM FILTER STATION INCL. AUXILIARY SYSTEMS FOR THE WASTE-TO-ENERGY PLANT WUPPERTAL

Scope of supply:

  Execution of the entire engineering scope incl. process engineering, plant- and detailed engineering

Supply and installation of the water-steam-cycle, connecting pipelines, steam-, condensate- and feed water system, cooling water system, civil construction, pipe bridge, turbine, demineralization system, condensate cleaning, chemical storage- and dosing system, pumps, E I&C (electrical incl. control technology), infrastructure

  Commissioning

Location: Wuppertal (D)

Execution period: 2017

 

 

Technical data:

  • Back pressure turbine: 8MW
  • Steam parameter high pressure steam: 34-36 bara, 385°C, up to 130 t/h
  • Steam parameter medium pressure steam: 7-17 barü 200-220°C